PROJECT

Verdigris Water Treatment Plant – Pretreatment Basin Expansion

Project Description

This project consists of constructing a new pretreatment basin to expand the pretreatment capacity from 20 mgd to 30 mgd. The pretreatment basin consists of rapid mixing, three-stage flocculation, and plate settlers with sludge collectors and pumps. The project also includes construction of a raw water flow meter vault, a control valve vault, new chemical feed pumps and accessories in the existing Membrane Building, a new electrical building, electrical and instrumentation and control work for the new facilities, and associated site work and yard piping.

Project Details

Location:

Broken Arrow, OK

Owner:

Broken Arrow Municipal Authority

Engineer:

HDR Engineering, Inc.

Contract Type:

Design-Bid-Build

Contract Amount:

$6,833,000